Building Department Review Times
It has been a crazy few months for the development community in Aspen! The building department has received an unprecedented amount of permit applications over the last few months. As such, review times are lengthy and these times should be built into your schedule for future permit submittal. We aren’t happy with these turnaround times and we know you aren’t either. We are making changes internally to improve these times, including reallocation of staff resources to focus on permit review.
Here are the current turnaround times from acceptance for review to first round of review for all permit types, as of Oct 1, 2020:
- Mechanical, Electrical, and Plumbing Permits: 2-3 Days
- Repairs — 1-2 Weeks
- Additional Information – 2 Weeks
- Re-Roof Permits – 2-3 Weeks
- IFFR Permits – 2-3 Weeks
- EPIC Permits – 2-3 Weeks
- Response to Comments – 7-9 Weeks
- Simple Change Orders – 7-9 Weeks
- New Minor Permits – 8-10 Weeks
- Major Change Orders – 9-11 Weeks
- New Major Permits – 10-12 Weeks